In a statement issued on Wednesday, November 18, 2026, the commission defended its handling of land valuation and asset verification, saying the responsibility for processing and disbursing compensation payments rests with the Kenya National Highways Authority (KeNHA).
NLC explained that its mandate is limited to assessing land and property belonging to affected residents, verifying assets and preparing compensation schedules. KeNHA is responsible for processing payments and releasing the money to Project Affected Persons (PAPs), in line with the World Bank's implementation requirements.
The clarification followed concerns raised by the World Bank over delays in compensating residents whose land is required for the Horn of Africa Gateway Development Project (HOAGDP).
In a letter addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport Cabinet Secretary Davis Chirchir and Lands Cabinet Secretary Alice Wahome, World Bank Division Director Qimiao Fan warned that unresolved compensation issues were slowing down construction.
The bank estimated that delays were generating additional project costs of more than KSh1.2 billion every month because contractors could not obtain unrestricted access to sections of land earmarked for construction.
It also disclosed that only 1,281 out of 1,669 identified project-affected persons had received compensation at the time of its assessment, raising concerns about the pace of land acquisition.
Responding to the concerns, NLC outlined the progress made across several sections of the highway, including compensation approvals and ongoing payment processes involving billions of shillings.
Along the Isiolo-Kulamawe-Modogashe section, the commission said KeNHA was awaiting the World Bank's no-objection approval to proceed with payments amounting to KSh554.9 million for 1,280 affected people.
For the Wajir-Kotulo section, NLC said it had approved compensation worth KSh824 million for 1,619 affected persons.
The commission also approved KSh497 million in compensation for 296 affected people along the Isiolo-Kachuru section.
Meanwhile, asset verification had been completed for more than 1,105 affected persons along the Dimu-Elwak section. NLC said the valuation exercise was expected to be completed by the end of November 2026.
The commission maintained that these activities demonstrated progress in the land acquisition process, despite the challenges affecting the wider project.
However, it identified several obstacles that have complicated compensation and delayed the release of land for construction.
These include court cases involving disputed compensation claims, insecurity in some areas, landowners who have not collected their compensation offers and difficulties tracing certain property owners.
The Isiolo-Mandera highway is part of the Horn of Africa Gateway Development Project, a major infrastructure programme intended to improve transport connections across northern Kenya and strengthen regional trade links.
The approximately 740-kilometre road was reported to be 60 per cent complete as of October 26, 2026.
It was initially expected to be completed by January 2028, but the completion timeline was subsequently pushed towards 2030 following project implementation challenges.
While NLC maintains that it has completed key valuation and approval processes, the World Bank's concerns point to the need for faster compensation payments to prevent further delays and additional project costs.