Elevated Shortcut: Nairobi’s 1km Viaduct Moves Into Next Stage

Written by

in

Nairobi’s 1km Kenyatta Avenue–Upper Hill viaduct reaches new construction stage

Interior Principal Secretary Raymond Omollo announced the latest milestone on Thursday, November 19, 2026, noting that the elevated link is designed to create a faster, more direct connection across notoriously congested junctions.

Implemented by the Kenya Urban Roads Authority (KURA) under a contract worth roughly Ksh2.99 billion (often rounded to Ksh3 billion) with China Road & Bridge Corporation (CRBC), the elevated structure forms the centerpiece of a broader urban road package spanning about six kilometres and incorporating pedestrian walkways and cycling facilities.

Once complete, the viaduct will carry traffic above busy intersections along Processional Way, Mamlaka Road, and Nyerere Road past All Saints’ Cathedral before linking toward Jakaya Kikwete Road, Ngong Road, and Valley Road.

For commuters, public service drivers, and business travelers moving between Upper Hill’s offices, the CBD, and surrounding neighbourhoods, bypassing those traffic lights promises predictable travel times during peak hours.

An ongoing construction of Kenyatta Avenue–Upper Hill Viaduct. PHOTO/https://web.facebook.com/drrayomollo

While officials have previously pointed to late-2026 and 2027 completion windows, lane restrictions and junction works have tested commuters’ patience along adjacent routes. Advancing into this next construction stage moves Nairobi closer to a grade-separated shortcut provided steady funding and disciplined execution carry the project through to opening day.

source:https://peopledaily.digital/news/nairobis-1km-kenyatta-avenue-upper-hill-viaduct-reaches-new-construction-stage

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *