NLC Breaks Silence on Isiolo-Mandera Road Delays as World Bank Warns of KSh1.2 Billion Monthly Loss

Written by

in

In a statement issued on Wednesday, November 18, NLC Chairman Abdillahi Saggaf Alawy provided an update on compensation activities, saying the commission had already completed several stages of identifying affected landowners, assessing properties and preparing payment schedules.

Alawy, however, clarified that NLC does not directly pay people affected by the construction works. Its mandate involves determining compensation amounts and preparing the necessary documentation, while the Kenya National Highways Authority (KeNHA) handles the actual disbursement.

Millions awaiting compensation

The commission reported progress across several sections of the 740-kilometre road corridor.

Along the Isiolo-Kulamawe-Modogashe stretch, KeNHA was awaiting World Bank approval to compensate 1,280 affected individuals, with the proposed payments totalling approximately KSh554.9 million.

For the Wajir-Kotulo section, NLC had approved compensation awards worth KSh824.8 million for 1,619 affected persons and forwarded the schedules to KeNHA.

Meanwhile, valuation activities along the Dimu-El Wak section were expected to be completed by the end of November following an exercise involving more than 1,105 affected individuals.

NLC also approved KSh497 million for 296 people affected along the Isiolo-Kachuru section, although payment was pending the availability of funds from KeNHA.

Why compensation is taking longer

The commission identified several obstacles complicating the exercise, including court cases, insecurity, disputed ownership, unresolved succession matters and compensation money that beneficiaries have yet to collect.

Some affected individuals have also undertaken speculative developments on their properties, further complicating the valuation process.

The clarification follows a warning from the World Bank that restricted access to construction sites across six active contracts could generate substantial additional expenditure.

The lender estimated that maintaining idle equipment, security operations, supervision and rising construction costs could consume approximately KSh1 billion monthly. Demobilising and later returning contractors could add another KSh207.5 million.

The KSh168 billion Horn of Africa Gateway Development Project is intended to improve transport links, digital connectivity and cross-border trade in northern Kenya.

Construction is approximately 60 per cent complete, with the overall project expected to be finalised around June 2030.