KenGen Adds 63.3MW to National Grid After Reviving Olkaria I Plant

Written by

in

thumbnail

Kenya’s oldest geothermal power station is back in operation following a three-year rehabilitation programme that has increased its electricity generation capacity, giving the national grid an additional 63.3 megawatts (MW).The Kenya Electricity Generating Company (KenGen) announced the completion of works at Olkaria I power station in Naivasha, Nakuru County, which was commissioned in 1981.