The disclosure followed an on-site tour conducted on Monday, November 16, 2026, by the National Assembly’s Departmental Committee on Social Protection, led by Chairperson Alice Ng’ang’a, alongside officials from the National Social Security Fund (NSSF), which is a key institutional investment partner in the public-private partnership project.
During the inspection of the 81-kilometre Rironi–Gilgil section, lawmakers were briefed that overall construction progress stands at approximately 40 percent, with contractors assuring the delegation that the entire stretch to Gilgil will be fully ready for traffic by March 2027.
The timeline provides crucial clarity following earlier government assurances by Roads and Transport Cabinet Secretary Davis Chirchir that completed lanes along the shorter Rironi–Naivasha segment would be opened temporarily before Christmas 2026 to ease festive congestion.
While engineers have completed over 90 percent of major earthworks and deployed additional asphalt pavers to lay up to one kilometre of surfacing daily after overcoming earlier global bitumen supply bottlenecks, active roadworks will persist beyond Naivasha toward Gilgil throughout the holidays.
Despite the phased schedule, Ng’ang’a’s committee endorsed NSSF’s investment in the 233-kilometre Rironi–Mau Summit corridor as a viable long-term venture, with the entire highway project targeted for full completion by June 2027.