NLC Explains KSh1.3 Billion Compensation Plan for Isiolo-Mandera Road

Written by

in

The National Land Commission (NLC) has defended its role in compensating landowners affected by the construction, of the Isiolo-Mandera highway following concerns raised by the World Bank over delays in the process.

In a statement issued on Wednesday, November 18, 2026, the commission dismissed claims that it was responsible for the delays, saying its mandate in the compensation process was limited to land valuations and preparation of compensation schedules.

NLC explained that it was responsible for assessing affected properties, verifying assets and determining the value of land and other developments belonging to Project Affected Persons (PAPs).

However, the commission said the processing and disbursement of compensation funds were handled by the Kenya National Highways Authority (KeNHA), following directives from the World Bank.

"The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HOAGDP)," the commission stated.

It added that KeNHA was responsible for handling payments to affected landowners as part of the project's implementation arrangements.

The clarification came after the World Bank raised concerns that delays in land compensation were affecting progress on the 740-kilometre Isiolo-Mandera highway.

In a letter addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport Cabinet Secretary Davis Chirchir and Lands Cabinet Secretary Alice Wahome, the bank's Kenya Division Director, Qimiao Fan, warned that the compensation challenges were slowing down construction.

The bank said contractors had not received unrestricted access to sections of land required for the project, making it difficult to carry out planned works.

It further warned that the delays were increasing project costs, with additional expenses estimated at more than KSh1.2 billion every month.

The concerns have placed renewed attention on the compensation process, which is a key requirement before contractors can access and work on the affected sections of the highway.

NLC's statement sought to distinguish its valuation responsibilities from KeNHA's role in processing and paying compensation.

LINK: https://www.kenyans.co.ke/news/129492-nlc-reveals-ksh13-billion-compensation-northern-kenya-road-project?utm_source=Facebook&utm_medium=MN&fbclid=IwZXh0bgNhZW0CMTEAcGRvZgRzcnRjBmFwcF9pZA80MDk5NjI2MjMwODU2MDkAAR_9JqiMVJ_z-G5zOcZISBX3ZN8HzVyLCLDmREldDLZUxFw5LcvC6JxJK9eYmQ_aem_ExMJuH8lACiYs-GrAhp3PQ