Eight Dead, No Approval: Forged Papers Exposed in Eastleigh Building Tragedy

Written by

in

Speaking before the Nairobi County Assembly's Urban Planning Committee on Monday, November 16, 2026, Assistant Director for Development Control Fredrick Ochanda said the county had never approved the building plans for the project.

According to Ochanda, the developer had initially applied to construct a 15-storey residential building on a property along Ninth Street, Eastleigh, identified as Plot No. 36/2/40.

The application was submitted by architect Emmanuel Mwangi Maina on behalf of the property owner, identified in the county records as John Mutie Musyoki.

Ochanda explained that the first application, submitted on November 25, 2024, proposed a building with one basement and 15 floors. However, the developer failed to pay the required application fee of approximately KSh2 million, meaning the application was not processed.

A second application was submitted on November 14, 2025, with a similar proposal. This time, an invoice of approximately KSh1.1 million was issued and paid.

However, the application was still not approved because it had several outstanding requirements that the developer needed to address.

These included removing shops proposed for the basement, providing adequate on-site parking and obtaining clearance from the Kenya Civil Aviation Authority (KCAA) regarding the proposed building height.

Ochanda told the committee that the developer had not fulfilled these requirements and that City Hall had never issued the necessary construction approval.

The county official further told legislators that documents presented as evidence of approval from City Hall were not genuine.

He said the developer allegedly used the documents to obtain registration from the National Construction Authority despite lacking the primary development approval required from the county government.

"Regarding the question of NCA approval, the letters in question did not originate from us. They were forgeries," Ochanda told the committee.

The NCA had confirmed that the project was registered on July 30, 2025, under registration number 53128815710410.

Its records identified 9th Street Plaza Limited as the developer and Stromax Holdings EA Limited as the contractor.

The discrepancy between the county's position and the documents allegedly used to secure NCA registration has become a major focus of the ongoing investigations.

The committee, chaired by Baba Dogo MCA Geoffrey Majiwa, has also intensified efforts to establish the individuals and institutions responsible for the development.

Majiwa said the developer, architects and contractors involved in the project had been invited to appear before the committee but had not attended the previous session.

He confirmed that fresh invitations had been issued for them to explain their respective roles.

Two individuals mentioned during the inquiry, Nairobi County Chief of Staff David Njoroge and Governor Johnson Sakaja's adviser Osman Khalif Abdi, were also expected to appear and respond to questions raised during the proceedings.

Majiwa said the committee wanted everyone mentioned in the investigation to be given an opportunity to explain their involvement before conclusions were reached.

During an earlier session, Acting Director for Compliance Tom Achar also told the committee that political interference had affected the operations of officials responsible for regulating developments in Nairobi.

The building collapsed on October 23, 2026, trapping workers and other people beneath tonnes of concrete and debris. Eight people were subsequently confirmed dead following rescue and recovery operations.

The tragedy renewed scrutiny of Nairobi County's building approval procedures, inspection systems and enforcement of construction regulations.

The Director of Public Prosecutions has directed the Directorate of Criminal Investigations to investigate possible negligence, omissions or misconduct involving public officials, developers and construction professionals connected to the project.

Investigators are expected to establish how the building proceeded to 18 storeys without the required approvals and whether failures by individuals or institutions contributed to the disaster.

The latest revelations have placed renewed pressure on City Hall and other regulatory agencies to explain how a development that allegedly lacked essential approvals continued despite enforcement interventions.

As the investigations proceed, the central question remains how the building was allowed to reach such an advanced stage of construction before the deadly collapse.