Christmas Travel Relief as Government Prepares to Open Parts of Rironi-Naivasha Highway

Written by

in

The move is aimed at easing congestion along the highway ahead of the festive season, when thousands of Kenyans travel from Nairobi to various destinations across the country, including the Rift Valley and Western Kenya.

In a statement issued on Saturday, November 21, the Ministry of Roads and Transport said construction works on the wider Rironi-Mau Summit highway were being accelerated to allow motorists to use sections that are already complete before Christmas.

The completed portions are expected to be opened before the final asphalt finishing works are undertaken, allowing traffic to resume on sections where construction has progressed sufficiently.

The Ministry said motorists would be informed about the specific sections being opened and the traffic arrangements that would guide movement through the construction zone.

Transport Cabinet Secretary Davis Chirchir is expected to provide further guidance on how motorists will navigate the reopened portions as contractors continue working on the remaining sections.

The announcement comes after the government missed an earlier October 30 deadline to complete the road section and allow motorists to use it. Despite the previous commitment, construction was still ongoing when the deadline passed.

On October 31, Chirchir announced a revised timeline, indicating that the government was targeting December to complete the dualling works and restore traffic along the highway.

The Rironi-Naivasha section stretches approximately 60 kilometres and is part of the larger 233-kilometre Rironi-Mau Summit highway project. The road is a major transport corridor connecting Nairobi to the Rift Valley and routes leading towards Western Kenya and Uganda.

The Ksh200 billion project involves expanding the existing highway to accommodate growing traffic volumes. The Rironi-Naivasha section is being upgraded into a four-lane road to improve traffic flow along the increasingly busy route.

China Road and Bridge Corporation (CRBC) is undertaking the construction works, which were officially launched in November 2025. The entire Rironi-Mau Summit highway project is scheduled for completion by June 2027.

However, motorists travelling during the Christmas period will still need to follow temporary traffic arrangements as construction continues on sections that have not yet been completed.