Ksh44 Billion to Walk Away? Inside the Quiet PPP Report Exposing Kenya’s Costly Adani Exit Mess

Written by

in

How stalled exit from cancelled Adani deal exposes Kenya to high claims

According to the Fifth Annual Report on the State of Public-Private Partnerships (PPPs) in Kenya for the 2025/2026 financial year, published by the PPP Directorate, the legal exit process between the Kenya Electricity Transmission Company (KETRACO) and Adani remained incomplete as of June 2026.

The report places the estimated termination liability for the two transmission-line projects at Sh43.943 billion—approximately Sh44 billion—a figure that surpasses the projects' estimated combined development cost of Sh41 billion.

The proposed 30-year concession covered the financing, construction, and operation of the 400kV Lessos–Loosuk and 220kV Kisumu (Kibos)–Kakamega–Musaga power lines, which had already reached commercial close prior to the November 2024 cancellation announcement.

Public finance and legal analysts warn that while a presidential directive halted implementation politically, complex international public-private partnership contracts remain legally binding until formal exit instruments, mutual settlements, or arbitral determinations are finalized.

Leaving termination procedures open-ended prolongs Kenya’s exposure to hefty contractual claims, accrued interest, and potential international arbitration penalties at a time when the National Treasury is already grappling with tight fiscal space and mounting debt-service obligations.

The revelation has reignited scrutiny over how large-scale infrastructure concessions are structured, vetted, and terminated without shifting disproportionate financial risk onto the public purse.

Economists note that even where public interest or governance concerns compel the state to cancel a project, swift and airtight legal closure is essential to prevent contingent liabilities from ballooning into actual budgetary shocks.

What are your thoughts about this articles? Share your reactions in the comment section and don't forget to share and follow for more updates.

https://www.standardmedia.co.ke/business/business/article/2001562819/how-stalled-exit-from-cancelled-adani-deal-exposes-kenya-to-high-claims

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *