Ndii Explains Why Bomas Costs More Than GTC Tower as Questions Over KSh45.1 Billion Emerge

Written by

in

The development in Nairobi has attracted attention following remarks by presidential economic adviser David Ndii, who defended its reported KSh45.1 billion cost against comparisons with the Global Trade Centre (GTC) Tower.

On Tuesday, November 17, Ndii challenged critics who had questioned why the Bomas project was more expensive than the GTC Tower.

He argued that the two developments could not be compared fairly without considering their sizes, noting that Bomas covers approximately 324,000 square metres, compared to 147,000 square metres for the entire GTC complex.

According to Ndii, the Bomas development is more than five times the size of the GTC Tower.

However, questions about the project's expenditure have persisted, particularly following changes to its initial budget.

In August 2023, the Cabinet approved an estimated cost of KSh31.7 billion. The latest reported figure of KSh45.1 billion represents an increase of KSh13.4 billion, or approximately 42.3 per cent.

The National Treasury's 2025/2026 Annual Public Debt Management Report placed the overall cost at approximately KSh42 billion, with the first phase estimated at KSh31.5 billion.

The report indicated that the project would be implemented through a public-private partnership arrangement. Private investors would finance the hospitality and commercial facilities, while the government would fund the main convention centre.

The Auditor-General also raised concerns about how the construction contract was awarded.

In a report covering the Ministry of Defence for the year ending June 30, 2025, the audit office established that direct procurement approval was granted on February 17, 2025, yet the procurement process had already started on February 13 and 14.

The Auditor-General said this was contrary to Section 69(2) of the Public Procurement and Asset Disposal Act, 2015.

The report further pointed out differences between the payment terms in the construction contract and the financing arrangement approved by Treasury.

The contract provided for nine instalments within 24 months, while Treasury had approved a deferred payment period of 10 years. The discrepancy could expose the government to additional charges if payments are delayed.

The Senate has also demanded documents relating to the project, including construction contracts, procurement records, invoices, payment details and approved designs.

Tourism Cabinet Secretary Rebecca Miano told senators in September 2026 that her ministry owned the project and oversaw its funding, while the Ministry of Defence held the main construction and procurement documents.

Construction delays have added to the concerns. The complex was reportedly 38 per cent complete as of June 2026, despite an earlier completion target within the 2025/2026 financial year.

The deadline was later pushed to December 31, 2026.

The project also received KSh1.5 billion against a KSh4.6 billion grant target in the 2025/2026 financial year, leaving a shortfall of KSh3.1 billion.

Bomas is expected to accommodate approximately 11,000 people and host major international conferences and business events.

However, the government still faces questions over the final expenditure, implementation of the project and whether the investment will generate sufficient economic benefits to justify the money spent.