Why Ndii’s defence of Ksh45.1B Bomas project leaves key questions unanswered

Written by

in

Why Ndii’s defence of Ksh45.1B Bomas project leaves key questions unanswered

President William Ruto’s economic adviser David Ndii has defended the cost of Kenya’s Bomas International Convention Complex, arguing that critics are making misleading comparisons with Nairobi’s Global Trade Centre (GTC) Tower.

But while Ndii maintains that the Bomas development is significantly larger, official records reveal deeper questions surrounding its cost, procurement, financing and implementation.

The project, whose reported overall cost has reached Ksh45.1 billion, has attracted scrutiny following an increase from the initial Cabinet-approved estimate of approximately Ksh31.7 billion in August 2023.

In a post on X on Tuesday, November 17, 2026, Ndii challenged comparisons between the two developments, arguing that their different sizes should be considered before judging their construction costs.

“Boss, this is called confirmation bias. You could’ve searched the sizes of each. Bomas Convention Centre is 324,000 square metres, more than 5 times the GTC Tower, and more than double the entire GTC complex (147,000 square metres),” Ndii wrote.

President’s economic advisor David Ndii : PHOTO/@DavidNdii/X

His argument is that comparing the reported Ksh45.1 billion Bomas cost with the approximately Ksh39 billion GTC Tower construction cost without considering their respective sizes produces a misleading conclusion.

However, the comparison raises an important measurement question.

Information presented to Parliament describes the Bomas development as covering approximately 323,500 square metres. This refers to the wider project area and cannot automatically be compared with the reported floor area of GTC Tower.

A proper cost comparison would require equivalent measurements, construction specifications and a breakdown of the facilities included in each development.

The bigger concern is the difference between the initial Ksh31.7 billion estimate and the reported Ksh45.1 billion overall project cost.

The difference is Ksh13.4 billion, equivalent to approximately 42.3 per cent of the original estimate.

However, the figures require careful interpretation because the project changed scope, contractor and financing arrangements.

Bomas International Convention Complex. PHOTO/@Williamsruto

The National Treasury’s 2025/2026 Annual Public Debt Management Report provides additional context. It describes Bomas as a public-private partnership under a plan, design, finance, construct, operate and transfer model.

Under the proposed arrangement, private investors are expected to finance the hospitality and commercial components, while the government finances the core convention centre.

The report puts the overall project cost at approximately Ksh42 billion, with the first phase estimated at Ksh31.5 billion.

This creates an important distinction between the initial phase, the main construction contract and the wider development. The different published figures cannot be treated as directly interchangeable without a detailed breakdown of their respective components.

The financial questions are compounded by findings in the Auditor-General’s report on the Ministry of Defence for the year ended June 30, 2025.

The report established that approval for direct procurement was granted on February 17, 2025, after procurement proceedings had already commenced, with tender invitation documents and a site visit certificate dated February 13 and 14.

The Auditor-General said this was contrary to Section 69(2) of the Public Procurement and Asset Disposal Act, 2015.

Auditor-General Nancy Gathungu addresses the Budget and Appropriations Committee on Tuesday, May 27, 2025. PHOTO/https://www.facebook.com/share/p/15MoxVfAEm/

The audit also identified inconsistencies between the construction contract’s repayment arrangements and Treasury’s financing approval.

While the contract provided for nine instalments within 24 months, Treasury had approved a 10-year deferred payment arrangement.

The Auditor-General warned that the government could incur penalties and charges if payments were delayed.

These findings do not establish that the project was overpriced or that corruption occurred. They do, however, raise questions about procurement compliance and the government’s financial obligations.

The project’s accountability arrangements have also attracted parliamentary scrutiny.

Tourism Cabinet Secretary Rebecca Miano told senators in September 2026 that her ministry owns the project and oversees its funding, while the Ministry of Defence holds the principal construction and procurement documents following a delegation of responsibilities.

The Senate during a past session. PHOTO/https://www.facebook.com/ParliamentKE

The arrangement prompted senators to demand the construction contract, financing agreements, procurement records, invoices, payment records, feasibility studies, bills of quantities and approved designs.

The Senate’s concern is particularly significant because the Tourism Fund is financing the development, yet the ministry responsible for the project’s ownership does not hold the principal construction contract.

There are also concerns about whether the investment will deliver its intended economic benefits within the expected timeline.

Business Daily reported in September 2026 that the complex was only 38 per cent complete as of June 2026, against a full completion target for the 2025/26 financial year.

The construction deadline was subsequently scheduled for December 31, 2026.

Funding has also emerged as a challenge. Bomas received Ksh1.5 billion against a Ksh4.6 billion grant target during the 2025/26 financial year, leaving a Ksh3.1 billion shortfall.

Construction progress at the Bomas International Convention Complex, where final interior finishes, external works and access roads are underway ahead of the December 2026 completion deadline. Photo: @ray_omollo/X

The delay and funding gap raise questions about whether the government can complete the project on schedule and meet its financial obligations.

Ultimately, Bomas is intended to strengthen Nairobi’s position as a regional destination for international conferences, business tourism and major events.

But its economic success will depend on more than its 11,000-person capacity. The government must demonstrate that projected conference demand, operating revenue and wider tourism benefits justify the investment.

Ndii’s comparison with GTC Tower highlights the importance of considering project size when evaluating construction costs. However, it does not resolve the questions surrounding Bomas’ revised cost, procurement history, financing arrangements and implementation delays.

For Kenyan taxpayers, the central issue remains whether the government can provide a transparent account of what the Ksh45.1 billion covers, why the project estimates changed and how the investment will generate sustainable economic returns.