The National Land Commission (NLC) has outlined the progress made in land valuation and compensation for the Horn of Africa Gateway Development Project following concerns by the World Bank over delays threatening to increase construction costs by about Ksh1.2 billion every month.
In a statement dated November 18, 2026, NLC Chairman Abdillahi Saggaf Alawy said the commission had made progress in identifying affected landowners, verifying assets, conducting valuations and preparing compensation awards along different sections of the 740-kilometre Isiolo-Mandera highway.
“The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HoAGDP),” read the notice in part.
Alawy clarified that the commission’s responsibility ends with valuation and preparation of compensation schedules, while the Kenya National Highways Authority (KeNHA) is responsible for processing payments and disbursing funds to Project Affected Persons (PAPs).
Under Package 1, covering the Isiolo-Kulamawe-Modogashe section, NLC said compensation payments were ongoing. KeNHA was awaiting World Bank no-objection approval for payments to 1,280 PAPs valued at Ksh554,969,790.
A further 111 affected persons had been forwarded for payment, while the commission had completed a compensation schedule addressing grievances involving 255 PAPs.
For Package 2, covering the 119-kilometre Wajir-Kotulo section, NLC said it had approved compensation awards for 1,619 PAPs amounting to KSh824,846,737.
The affected areas include Wajir, Lafaley, Tarbaj, Hungai, Wargadud, Kotulo Wajir and Kotulo Mandera. The approved compensation schedules had been forwarded to KeNHA for payment.
In Package 3, covering the Dimu-El Wak section, the commission conducted disclosure and asset validation between October 12 and 23, 2026. The exercise covered more than 1,105 PAPs across seven settlements, including Majani, Dimu, Garsesala, Dabacity, Kobo, Borehole 11 and El Wak Town.
NLC said valuation for the section was expected to be completed by the end of November 2026.
Separately, the commission had approved initial compensation awards for 296 PAPs along the Isiolo-Kachuru section, amounting to KSh497,072,500. The payments were awaiting the deposit of funds by KeNHA.
Work on the Modogashe-Samatar-Wajir section, however, was awaiting fresh facilitation from the highways authority.
The World Bank had earlier warned that restricted access to construction sites across six active contracts could result in recurring monthly costs of about KSh1 billion.
The additional expenditure covers supervision, security, idle equipment and price escalation. The bank also estimated that demobilisation and remobilisation could cost another KSh207.5 million, bringing the total financial exposure to approximately Ksh1.2 billion.
World Bank Division Director for Kenya Qimiao Fan noted that compensation funds had been available since 2024, but the process only began in November 2025.
He said implementation remained largely limited to the Isiolo-Modogashe section, where 1,281 of 1,669 eligible people had received Ksh456 million in compensation.
The concerns have placed the land acquisition process under scrutiny as construction continues along the major transport corridor linking northern Kenya to the border with Somalia.
In its response, NLC said land acquisition and compensation involved several agencies and required statutory approvals, availability of funds, resolution of grievances and clearances from development partners.
The commission identified several outstanding issues affecting the process, including litigation at the Garissa Magistrates Court over responsibility for compensation payments.
Other challenges include insecurity, particularly along the Wajir Town-El Wak corridor, speculative developments by affected landowners, missing persons and compensation awards that have not been collected.
The commission also cited unresolved succession cases involving deceased PAPs, which have complicated the release of compensation to beneficiaries.
NLC said it remained committed to working with KeNHA, the World Bank and other stakeholders to address the outstanding issues, speed up compensation and safeguard the rights of affected landowners.
The Horn of Africa Gateway Development Project is a major infrastructure investment valued at about KSh168 billion, which the World Bank has described as its largest single-sector investment in Kenya.
The project seeks to upgrade roads, improve digital connectivity and strengthen cross-border trade. Construction is reported to be about 60 per cent complete, with completion targeted for around June 2030.