In an update released on Saturday, November 21, the Ministry of Roads and Transport said construction works were being accelerated to allow motorists to start using sections that are nearing completion.
The ministry explained that portions requiring only final asphalt works would be made accessible to the public ahead of Christmas. The move is expected to reduce traffic congestion, improve mobility and make travelling along the busy corridor easier during the holiday period.
However, the Rironi-Naivasha stretch is expected to be completed by the end of 2026.
"The Government is fast-tracking works on the Rironi–Mau Summit Highway, with sections set to be opened to motorists ahead of the Christmas festivities to ease traffic congestion, enhance mobility and facilitate smoother journeys," the ministry stated.
Motorists have also been advised to remain cautious when driving through areas where construction is still ongoing and obey instructions from traffic marshals.
The announcement comes amid growing concerns over delays in completing the Rironi-Naivasha section, which had initially been expected to be ready by October 31.
Roads and Transport Cabinet Secretary Davis Chirchir previously attributed the delay to disruptions in the supply of bitumen, a major material used in road construction.
He disclosed that the cost of the petroleum product had increased from Ksh90 per kilogramme six months earlier to approximately Ksh200, putting additional pressure on the project.
Chirchir linked the supply challenges to disruptions around the Strait of Hormuz, which affected the availability and cost of bitumen.
The ministry and the contractor have since been working on measures to address the rising expenses and minimise further delays.
The highway expansion is expected to improve transport between Nairobi and the Rift Valley while supporting movement of people and goods along the corridor.